ZzzZzz......

Nothing has changed since our first post on 3.6.13.  For some reason the forms don't match the finished floor elevation on the plans.  Apparently the City inspector is not accepting any of the builder's explanations/solutions for the discrepancy.  Foundation guy and architect are meeting today to come up with another solution to take to the City.  At this rate, the foundation won't be poured until mid-April or later!

3.20.13 - Looking east at house footprint.